Thursday, January 20, 2011

We Have A Roof... And Deck!

The last week and a half have been busy around here and as always, the weather has been on our minds.  After the framing was finished, we anxiously watched the days go by with pooled water sitting on the subfloor from all the rain we had.  The forecast had a snow warning in effect and we anticipated a good 8"s for our neck of the woods... the worst part being that because we are in the mountains, the snow usually sticks around once it's fallen.  This would mean the roofers could be delayed for some time and our framing and subfloors would stay wet until the roofers were able to work.  The roofers were originally scheduled to arrive on friday the 6th but the plan changed and they decided to come that sunday instead. On saturday evening (jan.7th), we were hanging out in Abbotsford with our pint-sized friend Claire when the snow began to fall.  By 11:00 that night, there was almost five inches on the ground.  We imagined about a foot of snow at our place but as we drove home, we were both suprised and relieved to find barely a dusting had fallen on the house.  It was too late in the evening to call our site superintendant so I sent an email explaining our good fortune and decided to call him early in the morning so that he could let the roofers know that the roof was clear.  In the end, the roofers didn't come, probably figuring we had as much snow as they did in town. 

Later sunday afternoon, someone from the roofing company came out to inspect the house, presumeably to make sure the roof was clear;  We were a bit doubtful that they would be coming monday because the temperature had dropped below zero and the roof had become a sheet of ice.  Monday morning we woke to Trouble's alert bark and found a crew of seven roofers in the driveway unloading their gear.  This was a huge relief because there was another snow warning in effect and we figured this was going to be the big one that would bring the project to a screeching halt.  It can be extremely distracting watching the guys work on the house and knowing snow was coming made it very hard to focus on anything other than the progress they were making.  There had been some hope that the roof could be finished in a single day with such a large crew but because our roof has alot of surface area with the surrounding porch overhang, the day ended with about seventy percent of the roof finished.  As luck would have it, and we've had a good share of it, we only received about two centimeters of snow overnight, which the roofers were able to sweep clean in the morning thanks to spiked work boots.  By 1:00 the workers had finished the roof and were packing up their gear;  We excitedly went to inspect their work just as the snow began to fall in earnst.

Now that the interior of the house was protected and could start drying out, the plumber (Riley) was the next tradesman to arrive.  The plan was to rough in the whole house and then pour concrete for the basement slab and porch and decks.  Once again, the weather became a factor...  First off, the basement gravel was still frozen from the cold weather we were having so it made the job of digging trenches that much more difficult. When Riley and his crew finally broke through the frozen crust and had their trenches dug, they immediately began to fill with water from all the rain we had.   On top of that, the pipes that exited through the bottom of the house weren't quite deep enough and didn't provide enough grade for the length of run and wouldn't pass inspection the way they were. 


Pumper Truck Pouring Concrete
Neil was quickly called back into action the following day and dug out around the exit port in the foundation so that the pipes could be buried a little deeper.  This drained the water from the trenches and allowed Riley to get the right grade for the drainage pipes.  The foundation was again backfilled and Riley and his crew finished off the day by roughing in the main-floor plumbing.  The next morning Riley was knocking at the door to use the telephone as we don't get cell reception where we are... I overheard him telling his boss that they were again having problems with water in the trenches since the foundation had been backfilled again.  Essentially, after he laid the pipes, they began to float in the water which changed their grade...

Exposed Aggregate
they had become too horizontal and wouldn't drain properly when he tested them.   After discussing the problem with him, we decided Neil would have to come back and reopen the area he had backfilled the day before.  Fortunately, Neil was available and twenty minutes later he was onsite digging a trench from the foundation to where our drain pipes are.  The trench once again resolved the issue and by the end of friday, the plumbing was ready for a monday morning inspection before being buried.  Monday morning the inspector arrived and the whole system was approved.



When planning the house, we decided that we wanted a deck surface that would be low maintenance and have a clean appearance.  Exposed aggregate concrete was an easy decision as our previous house's deck had been finished that way and it was a look we liked.  The area below the deck is meant to be used as a carport and we wanted to make sure the area was sealed from the rain that would hit the deck above... this meant sealing the deck before the concrete was poured.  Monday morning Jordan and his crew were back to finish laying the plywood on the framed deck.  After the plywood was secured a frame was built off the end of the deck and then covered with heavy plastic to protect the plywood from the rain.  The following day a crew arrived to seal the deck. 

A heavy vinyl was applied to the whole deck and up the walls and support posts and then all seams were heat sealed so the entire deck and walk around porch was completely sealed.  A little later Dan showed up to nail boards around the perimeter of the porch and deck to contain the concrete when it was poured.  The concrete guys were busy the following day so plan was to do the pour on thursday.  This morning, a six man concrete crew arrived along with a pumper truck and the first of three concrete trucks.  After setting up their equipment they started by pouring the concrete on the back side of the house and then moved to the deck and then front porch.  Two concrete trucks were emptied and about an hour later the guys had out their floats and were smoothing out the surface of the concrete. 

I wasn't familiar with how exposed aggregate decks were created so I got on Google last night and did a bit of reading.  I wasn't really sure how the small exposed stones were placed... were they already in the concrete or were they sprinkled on afterwards?  It turns out the stones are premixed in the concrete which allows you the choice of various exposed surfaces... we had decided on the typical small, smooth stones.  Since the stones are premixed in the concrete, the question becomes, how are they later exposed?  A surface retardant is used that slows the surface of the concrete from setting while the rest of the concrete sets in about four hours. 

When the concrete has set enough that it can be walked on, a brush and a pressure washer is used to wash away the very thin surface of the concrete that had the retardant on it, and expose the aggregate contained within.   Later, after the concrete is fully set, a sealant will be applied that will give the aggregate a wet, shiny look to it and help protect the concrete from the elements. 
The basement slab was also poured today and while it wasn't overly exciting to watch, it's nice seeing the finished slab.  Next week the plumber will come and finish installing and testing the water lines and later in the week the electrician will begin wiring the house... that means more decisions to be made on where we want outlets and if we want to prewire walls for sconces, etc...  

















5 comments:

  1. Hi Darcy and Margaret! (Darcy's cousin Sheri, here) Your blog is so great, we can't wait to see the continued progress. So exciting!

    Love from your Calgary family!
    Sheri and Mark (and Jaida, Zoe and Maya too)

    ReplyDelete
  2. Hey Calgary family!

    thanks for the comment... We sometimes wonder if anyone actually reads this blog and after seeing your blog (dad and Charlotte sent a link) I'm honestly a bit ashamed at the sorry state of ours.

    Sorry we missed your dad's birthday but we're sure going to try and make it out there this summer. There's a standing invitation if you guys make it out here first... it be nice to catch up for the last fifteen years or so :)

    Darcy & Margaret

    ReplyDelete
  3. I read it, too! It's nice to see it looking like a proper house. Whaddya doin' building a house in winter? You crazy kids!

    It's looking good, guys.

    Joanne

    ReplyDelete
  4. Hey Joanne,

    thanks for confirming the blog isn't in vain! We're wondering the same thing about building in winter, at least when it's done it won't be full of mosquitoes! Friday was a great day because after the basement slab was poured, the framers came in and framed the basement, including the stairs to the main floor... no more sliding around in the mud when we want to have a look inside... it's the small victories we try to focus on.

    Darc

    ReplyDelete
  5. Your blog is not a sorry state! LOL...It's so interesting and makes me laugh. It also makes me want a new house, which may not thrill Mark. For now, we might just focus on finishing our basement, slowly. If and when Mark starts on that, i'll put updates on my blog too. Can't wait to read more!
    Sheri

    ReplyDelete